ASG Plastic Factory targets March 2027 completion for fourth plant
ASG Plastic Factory Co., a Saudi packaging and pipes group, expects its fourth factory to be completed in March 2027, adding capacity equal to about 25-30% of group output; the project was 55% complete at end-September 2026. Construction of a fifth factory, on land leased from industrial authority MODON in June 2026, is due to start in the first quarter of 2027, with operations from the second quarter of 2028. Both expansions are financed from retained earnings and operating cash flow.
Why this mattersAdds Saudi plastic packaging capacity as customers shift to local suppliers for supply security, though utilisation has fallen to 78% while new lines ramp up.
- Fourth factory (third expansion project) expected complete March 2027, adding 25-30% of group output; progress at 55% by end-September 2026.
- Fifth factory construction to start Q1 2027, complete Q1 2028, operations to begin Q2 2028, after leasing land from MODON in June 2026.
- Operating profit rose 39% YoY in 9M 2026, with sales and net profit already above full-year 2025 levels.
- Packaging segment revenue up 51% YoY and net profit up 40% YoY, accounting for about 75% of group revenue and 82% of net profit in 9M 2026.
- Production volume reached about 10,700 tonnes in 9M 2026, up 33% YoY, with capacity utilisation at 78% versus 89% in 2025.
- Expansions are financed through retained earnings and operating cash flows, according to CEO Alanoud Al-Nasr Allah.