Hubei Jingxiang unit nears trial runs at 200,000-tonne recycled PET flake plant
Hubei Jingxiang New Materials' subsidiary in Tianmen, Hubei is building a recycled PET plant that is now 70% complete, with two of nine planned production lines due to begin trial operation in December 2026. The full nine-line plant, expected on stream by March-April 2027, will process 240,000 tonnes of waste PET bottles a year into 200,000 tonnes of recycled PET flake for textile, automotive and packaging customers.
Why this mattersA 200,000 tonne/year recycled PET flake plant adds meaningful feedstock supply for packaging and fibre producers in China, supporting recycled-content goals downstream.
- Construction and equipment installation at the recycled PET project in Tianmen, Hubei are 70% complete as of 25 November 2026
- Two of nine planned production lines are due to begin commissioning from late November 2026, with trial operation starting early December 2026
- Full operation across all nine lines is expected between March and April 2027
- Once fully ramped, the plant will process 240,000 tonnes of waste PET bottles a year to produce 200,000 tonnes of recycled PET flake
- Estimated annual output value is about USD 180m (CNY 1.2bn) at full capacity
- New lines are designed for about 40% lower energy use and about 50% fewer labour hours than the company's existing conventional lines