Time Technoplast commissions 6,000-tonne pails plant in Gujarat
Time Technoplast has completed a greenfield plant at Bhilad, Gujarat, for conical polymer pails and injection-moulded packaging, with production due to start on 25 September 2026. The fully automated, robotics-equipped facility has an annual capacity of 6,000 tonnes and cost approximately INR 24 crore, with expected turnover of about INR 100 crore at 90% utilisation.
Why this mattersAn INR 24 crore line carrying about INR 100 crore of turnover at 90% utilisation adds Indian industrial pail capacity at low capital intensity.
- Plant located at Bhilad, Gujarat, India, completed within scheduled time.
- Production start scheduled for 25 September 2026.
- Annual production capacity is 6,000 tonnes for conical polymer pails and injection-moulded products.
- Investment of approximately INR 24 crore.
- Expected turnover of approximately INR 100 crore at 90% capacity utilisation.
- Facility is fully automated and uses robotics to cut human intervention and administrative costs.