Kazakhstan's Ministry of Ecology and Natural Resources has released 122.6 billion tenge in recycling-fee revenue to fund 34 waste management infrastructure projects, part of 67 approved projects worth 440 billion tenge. State-linked EPR operator Zhasyl Damu is financing new recycling plants, sorting complexes and equipment purchases, adding a combined 1.08 million tonnes per year of sorting and recycling capacity.
Why this mattersA large recurring recycling-fee pool is being channelled into sorting and recycling capacity, a funding model other extended-producer-responsibility regimes may watch.
- 122.6 billion tenge allocated to 34 projects as of 27 October 2026
- 67 projects worth 440 billion tenge approved in total by the Investment Headquarters
- Six funded projects add 650,000 tonnes/year of sorting capacity
- 18 projects add a combined 435,000 tonnes/year of recycling capacity
- 10 projects fund purchase of 177 units of specialised equipment
- 15 projects already commissioned, adding 290,000 tonnes/year sorting and 19,300 tonnes/year recycling capacity
Kazakhstan's Ministry of Ecology and Natural Resources has approved, by order of 9 October 2026, a standard contract governing utilisation (recycling) fee payments between operator Zhasyl Damu and producers and importers, effective 24 October 2026. The contract covers products and packaging subject to extended producer responsibility and sets procedures for filing applications, invoicing within three working days, payment and issuance of a compliance certificate.
Why this mattersProducers and importers selling packaged goods into Kazakhstan get a fixed EPR payment procedure, and the operator can reject applications with incomplete or inconsistent documents.
- Standard contract approved by Ministry of Ecology and Natural Resources order No. 264 of 9 October 2026
- Takes effect 24 October 2026
- Applies to products and packaging under extended producer responsibility (EPR)
- Operator Zhasyl Damu must issue an invoice within three working days of a correctly completed application via app.recycle.kz
- Extended producer responsibility obligations are considered fulfilled from the date the certificate is issued
- Producers and importers must ensure the certificate is passed to the end buyer when products are sold
Kazakh company Capital Plast KZ is constructing a new mill in Aktobe to make corrugating medium and testliner from recovered paper, the regional administration said. The plant, costing about KZT 10.3bn, is due to open in 2027 and will employ more than 300 people once at full capacity.
Why this mattersNew recycled-fibre capacity reduces reliance on imported containerboard and gives Kazakhstan's corrugated sector a local source of recovered-paper-based materials.
- Investment is approximately KZT 10.3 billion
- Plant opening is planned for 2027
- More than 300 jobs expected once the plant reaches full capacity
- Planned output is up to 18,000 tonnes per year of corrugating paper
- Planned output is up to 24,000 tonnes per year of testliner board
- A boiler house is already built; foundation and pile work is underway
- State recycling-fee operator Jasyl Damu is financing the Aktobe plant