Daio Paper orders biomass energy plant for Mishima mill from Takuma
Daio Paper has placed an EPC order with Takuma for a self-consumption energy plant at its Mishima mill in Shikoku Chuo City, Ehime Prefecture, to be delivered in 2030. The plant will burn paper-mill waste, wood biomass, RPF and tunnel-compost fuel derived from municipal waste, replacing the mill's existing coal boiler as part of the group's drive to reach carbon neutrality by fiscal 2050.
Why this mattersA leading Japanese paper group's shift from coal to multiple non-fossil fuels at a major mill signals a capital path other Asian paper producers may follow to cut fossil CO2.
- Daio Paper ordered the EPC contract for a self-consumption energy plant at its Mishima mill in Ehime Prefecture
- Delivery of the plant is planned for 2030
- The plant will supply steam to new power generation equipment using paper-mill waste, wood biomass, RPF and tunnel-compost fuel from Shikoku Chuo City municipal waste
- The project replaces the mill's existing coal boiler
- Daio Group targets carbon neutrality for production-related fossil CO2 emissions by fiscal 2050
- Takuma was selected for its technology to stably co-fire fuels of differing characteristics
Sources
zaikei.co.jp
JA