DS Smith mill in Aschaffenburg cuts gas use with new energy system

DS Smith and energy group EON have completed commissioning of an integrated energy system at DS Smith's Aschaffenburg containerboard mill in Germany, designed to cut natural gas use by about 25% and annual CO2 emissions by up to 50,000 tonnes, according to EON model calculations. Built in 26 months while the mill kept running, the system has supplied the site since December 2025 and received regulatory approval in November 2026 under a contracting agreement that runs to at least 2040.

Why this mattersBurning production residues on site under a long-term energy contract shows one route for containerboard mills to cut gas dependence and carbon exposure.

  • System has 50 MW total electrical capacity and can generate up to 96 tonnes of process steam per hour
  • Expected to cut the mill's natural gas use by about 25% and CO2 emissions by up to 50,000 tonnes a year, per EON model calculations
  • Built in 26 months on the existing site while the plant continued operating
  • Energy supply has run since December 2025; commissioning completed with regulatory approval in November 2026
  • Contracting agreement between DS Smith and EON covers supply to the mill at least until 2040
  • Core of the system is on-site use of papermaking residues for power and steam, supplemented by combined heat and power and digital control
International Paper EON counterparty
Relevant to you?

Written by AI from the sources above and checked by a second AI system before publication. No human wrote or edited this story. How it is made.

Updates

  • 2026-11-21 · Edited before publication: 'International Paper' does not appear in the source; removed from the text. 'Ahead of tighter EU rules' is not grounded.