InfraLeuna commissions wastewater plant for UPM biorefinery at Leuna

InfraLeuna, operator of the Leuna chemical park in Germany, has commissioned a purpose-built anaerobic wastewater pre-treatment plant for UPM's biochemicals biorefinery, investing EUR 42.7m in total, EUR 36.7m for the plant and EUR 6m for biogas feed-in infrastructure. The unit can treat up to 4,000 cubic metres of wastewater a day, cuts organic load by at least 80 percent, and generates about 6 MW of biogas fed into the site's gas grid, with commissioning proceeding in stages as UPM ramps up discharge volumes.

Why this mattersThe dedicated treatment and energy-recovery infrastructure removes an operating bottleneck for UPM's large-scale biochemicals plant, a reference project for bio-based inputs relevant to packaging.

  • InfraLeuna invested EUR 42.7m in total: EUR 36.7m for the plant and EUR 6m for a biogas feed-in system.
  • The plant treats up to 4,000 cubic metres of wastewater a day from UPM's biorefinery at Leuna, Germany.
  • The process cuts chemical oxygen demand by at least 80 percent and generates about 6 MW of biogas continuously, fed into the site's natural gas grid.
  • Commissioning is proceeding in phases as UPM gradually increases wastewater discharge while bioreactors are seeded with specialised anaerobic bacteria.
  • The plant was custom-built by InfraLeuna for UPM's biorefinery process rather than as a standard design.
  • The Leuna biorefinery is described as Europe's largest investment in biochemicals.
UPM InfraLeuna counterparty
Relevant to you?

Written by AI from the sources above and checked by a second AI system before publication. No human wrote or edited this story. How it is made.

Updates

  • 2026-10-07 · Edited before publication: Figures (EUR 36.7m plus EUR 6m, 4,000 m3/day, at least 80% COD reduction, c.6 MW biogas, phased commissioning) check out. One key fact attributes the 'Europe's largest biochemicals investment' claim to UPM; the source states it impersonally. Bullet corrected.