Klabin starts new USD 290m recovery boiler at Monte Alegre mill
Klabin has begun operating a new recovery boiler at its Monte Alegre pulp and paper mill in Telemaco Borba, Brazil, replacing a unit that had run since 1978. The boiler, supplied by Valmet as part of a USD 290m (BRL 1.7bn) modernisation begun in July 2024, started up on 15 October 2026, 47 days ahead of schedule, and can process 1,950 tonnes of dry solids per day.
Why this mattersReplacing a recovery boiler in service since 1978 secures chemical recovery and steam at Monte Alegre for decades and reduces the mill's fossil-fuel use.
- The project cost USD 290m (BRL 1.7bn) and began in July 2024.
- The new boiler, supplied by Valmet, started operating on 15 October 2026, 47 days ahead of schedule.
- It replaces Recovery Boiler 1, in service since 1978, at the Monte Alegre mill in Telemaco Borba, Parana.
- Capacity is 1,950 tonnes of dry solids processed per day.
- Construction involved more than 5,000 temporary workers, peaking at 1,300 simultaneous workers.
- The modernisation also updated the mill's distributed control system and added a crystallisation plant for chemical recovery.