MEPCO delays Saudi tissue line and containerboard machine startups

Saudi Arabia's Middle East Paper Co. (MEPCO) has pushed back the startup of its sixth tissue line (TM6) at subsidiary Juthor Paper in King Abdullah Economic City to Q1 2027 from Q3 2026, citing supply-chain disruption linked to regional geopolitical conditions. The company also delayed its PM5 recycled containerboard machine at its Jeddah mill to Q1 2028 from Q4 2027 and raised its estimated cost to SAR 1.881 billion from SAR 1.78 billion, while the TM6 budget of SAR 345 million is unchanged.

Why this mattersThe slippage delays new containerboard and tissue capacity reaching the Middle East market and postpones the projects' contribution to MEPCO's earnings.

  • TM6 trial production delayed to Q1 2027 from Q3 2026, commercial output also targeted Q1 2027
  • TM6 will add 60,000 tonnes/year of tissue capacity, doubling Juthor's output to 120,000 tonnes
  • TM6 investment unchanged at SAR 345 million
  • ANDRITZ supplies the TM6 Prime Line W 2200, designed for 2,100 m/min at 5.47 m width
  • PM5 recycled containerboard machine at Jeddah delayed to Q1 2028 from Q4 2027
  • PM5 estimated cost raised to SAR 1.881 billion from SAR 1.78 billion, machine capacity 450,000 tonnes/year
  • PM5 engineering works are 98% complete
  • Cost increase attributed to higher civil construction expenses, enhanced power and steam solutions, and rising global shipping and logistics costs
  • Updated internal rate of return for the PM5 project is estimated at 12%
  • SAR 465m (USD 124m) of capital-increase proceeds allocated to PM5, including SAR 291m transferred recently
  • Expected PM5 project internal rate of return stands at 12%
  • PM5 will produce a new 70 GSM grade versus the 90-100 GSM range currently sold domestically
  • Company reported good profits in H1 2026 despite higher raw material, energy, logistics and insurance costs
  • Updated project internal rate of return for the PM5 containerboard machine is now 12%.
  • The containerboard project was first announced in April 2024 with 450,000 tonnes of capacity; the tissue line was approved in August 2024 at subsidiary Juthor.
  • MEPCO says both delays will push back the positive earnings and EBITDA contribution from the two lines.
  • MEPCO's statement cites PM5 capacity of 475,000 tonnes per year of recycled containerboard
Andritz counterparty Middle East Paper Co.
Relevant to you?

Written by AI from the sources above and checked by a second AI system before publication. No human wrote or edited this story. How it is made.

Updates

  • 2026-10-03 · Further coverage added: argaam.com
  • 2026-10-04 · Update: MEPCO details the PM5 cost rise and delay: engineering is 98% complete, with the overrun blamed on higher civil construction costs, enhanced power and steam solutions, and rising shipping costs, and the project's estimated internal rate of return now stands at 12%.
  • 2026-10-05 · Update: Mepco says it has funded part of the PM5 cost increase from capital-raise proceeds and still expects a 12% project return despite the delay.
  • 2026-10-07 · Update: MEPCO says the delayed startups will also push back the projects' positive earnings and EBITDA contribution, with the containerboard machine's updated internal rate of return now put at 12%.
  • 2026-10-09 · Update: MEPCO's 30 September statement on the PM5 containerboard machine delay to Q1 2028 cites a planned capacity of 475,000 tonnes a year, against the 450,000 tonnes previously reported.