Metsä Fibre to feed Rauma pulp mill surplus heat into district heating
Metsä Fibre and local utility Rauman Energia are preparing to feed surplus heat from the recovery boiler at the Rauma pulp mill into the town's district heating network. The district heating station has arrived on site and is being connected; testing starts in early December and the system is due in production use by the end of December 2026. The heat is expected to cover about 10-20% of Rauman Energia's total heat demand.
Why this mattersRecovery-boiler heat sold to the local grid turns a mill by-product into a utility supply covering 10-20% of Rauma's district heating demand.
- Heat comes from the Rauma mill's recovery boiler, part of the pulp mill's chemical cycle
- Expected to cover about 10-20% of Rauman Energia's total heat demand
- Testing to start in early December 2026, with production use targeted by end-December 2026
- Connection points to the mill's steam and condensate systems were built during the 2025 annual maintenance shutdown
- On-site district heating pipework began in January 2026 and was completed in spring 2026
- Metsä Fibre had 2025 revenue of EUR 2.6bn and about 1,400 employees; Metsä Group revenue was EUR 5.8bn