Norske Skog approves USD 88.9m rebuild of Saugbrugs PM6 for kraftliner

Norske Skog has approved an investment of up to USD 88.9m (NOK 850m) to rebuild paper machine 6 at its Saugbrugs mill in Halden, Norway, converting the idled unit to flexible production of TMP-based kraftliner or SC magazine paper. Start-up is planned for the first half of 2028, after which production on PM4 and PM5 will cease permanently.

Why this mattersConverting a publication-paper machine adds up to 300,000 tonnes of kraftliner to European supply and permanently removes the PM4 and PM5 graphic paper lines.

  • Investment of up to USD 88.9m (NOK 850m) approved for the PM6 rebuild at Saugbrugs, Halden, Norway.
  • Rebuilt PM6 capacity up to approximately 300,000 tonnes/year of TMP-based kraftliner or approximately 230,000 tonnes/year of SC magazine paper.
  • PM6 has been offline since a rockslide at the site in April 2023.
  • Start-up of the rebuilt machine is planned for the first half of 2028.
  • Production on PM4 and PM5 will cease permanently once PM6 starts up.
  • Financing plans include a sale and leaseback of the PM6 building and property and a potential sale of the mill's administration office.
  • An 80-100 MW data centre opportunity at the Saugbrugs site is under exploration as part of financing for the PM6 rebuild
Norske Skog
Relevant to you?

Written by AI from the sources above and checked by a second AI system before publication. No human wrote or edited this story. How it is made.

Updates

  • 2026-10-09 · Further coverage added: euwid-paper.com
  • 2026-10-12 · Edited before publication: Conversion error: NOK 850m at USD 1 = NOK 9.562 is USD 88.9m, not USD 88.7m. Corrected in headline, summary and first key fact; all other content is grounded in the Paper Advance and EUWID excerpts.
  • 2026-10-15 · Update: Norske Skog says financing for the PM6 rebuild is also being explored via an 80-100 MW data centre opportunity at the Saugbrugs site, alongside the previously announced property sale and leaseback.