Suzano's Aracruz tissue mill completes first year after reaching full capacity five months early

Suzano's tissue mill in Aracruz, Brazil, reached 100% of its installed capacity within seven months of starting up, about five months ahead of schedule, the company said as the plant marked one year of operation on 18 November 2026. The USD 110m (BRL 650m) mill adds 60,000 tonnes a year of tissue capacity, taking Suzano's total installed tissue capacity to 340,000 tonnes a year.

Why this mattersA faster ramp-up strengthens Suzano's shift from pulp into branded consumer tissue, improving the economics of its forward-integration strategy.

  • Aracruz mill completed one year of operation on 18 November 2026
  • Investment of USD 110m (BRL 650m) added 60,000 tonnes a year of tissue capacity
  • Full installed capacity reached in seven months, about five months ahead of plan
  • Suzano's Cachoeiro de Itapemirim mill, opened 2021 with 30,000 tonnes a year capacity, took about 18 months to reach full output
  • Suzano's total installed tissue capacity now stands at 340,000 tonnes a year
  • Aracruz supplies tissue parent rolls to Cachoeiro, replacing volumes previously sent from Suzano's Mucuri unit in Bahia
Suzano
Relevant to you?

Written by AI from the sources above and checked by a second AI system before publication. No human wrote or edited this story. How it is made.

Updates

  • 2026-11-26 · Edited before publication: Source says Suzano's installed tissue capacity rose to 340,000 t a year overall; its Espirito Santo capacity is the two mills (30,000 t + 60,000 t), not 340,000 t.
  • 2026-11-26 · Edited before publication: Full capacity was reached months ago; the news is the first-anniversary report, so 'hits' in the present tense misled. Lowered to 2: a 60,000-tonne mill already running, with no new investment. The Markets & Customers topic is not supported.