Eldorado Brasil Celulose's board has authorised preparations for merging the company into J&F, which is centralising the group's finances and has already absorbed Ambar Energia. J&F became sole owner in May 2025 by buying Paper Excellence's stake for BRL 15bn (USD 3.0bn), but the planned second line at Tres Lagoas, held up by the dispute since 2018, still has no public start or completion date. Net debt rose to BRL 9.7bn (USD 1.9bn) at end-2025 from BRL 966m (USD 192m) a year earlier.
Why this mattersAn open-ended delay to 2.6 million tonnes of short-fibre capacity defers a large block of expected global pulp supply growth while Eldorado's net debt has risen tenfold.
- Eldorado's board authorised preparing the company's merger into J&F, which is centralising group finances; Ambar Energia has already been merged in.
- The second Tres Lagoas line would add 2.6 million tonnes/year, taking short-fibre capacity to about 4.4 million tonnes; it has no public start or completion date.
- The line is part of a BRL 25bn (USD 5bn) programme covering the mill, forests and a railway, unveiled in 2024.
- J&F closed its purchase of Paper Excellence's stake in Eldorado for BRL 15bn (USD 3.0bn) in May 2025.
- Net debt reached BRL 9.7bn (USD 1.9bn) at end-2025, up from BRL 966m (USD 192m) a year earlier.
- Eldorado issued BRL 13bn (USD 2.6bn) of commercial notes in June 2025 to fund the stake purchase; by July they had been replaced with longer, cheaper facilities.
- Eldorado's pulp production was stable in 2025 despite the ownership dispute.
- BNDES approved USD 188m (BRL 1.05bn) in December 2025 for an 86.7km rail link to the Aparecida do Taboado terminal
- Suzano started its 2.55m tonne a year Ribas do Rio Pardo pulp plant in 2024
- Arauco is developing the 3.5m tonne a year Sucuriu pulp project in Brazil
Suzano is attempting a further pulp price increase in October, targeting USD 600 per tonne for short-fibre pulp in China, after successfully pushing through a rise in September, according to a BTG Pactual note following meetings with Suzano executives in New York. The bank cites lower port inventories, delays to Asia Pulp and Paper's OKI II project and about 1.3 million tonnes of permanent long-fibre capacity closures as supporting near-term prices, but Suzano itself warned that new supply due in 2027, including Arauco's 3.5 million tonne Sucuriu plant and the delayed 1.4 million tonne OKI II project, could outpace demand growth of only 1-1.5 million tonnes a year and push prices lower again. Suzano said it is prioritising debt reduction and integration of its Kimberly-Clark joint venture over new capacity investment, expecting leverage to peak in the third quarter of 2026.
Why this mattersBuyers face higher pulp costs now, while 2027 capacity additions far exceed structural demand growth of 1-1.5m tonnes a year.
- Suzano is targeting USD 600 per tonne for short-fibre pulp in China in the October price round, after implementing a September rise, per BTG Pactual.
- Arauco's Sucuriu plant in Mato Grosso do Sul is expected to start in H2 2027 with capacity of 3.5 million tonnes of pulp a year.
- Asia Pulp and Paper's OKI II project, delayed to 2027, is expected to add a further 1.4 million tonnes of capacity.
- About 1.3 million tonnes of long-fibre pulp capacity have been permanently closed, supporting the recent price recovery.
- Structural pulp demand growth is estimated at only 1-1.5 million tonnes a year, below planned new supply.
- Suzano expects its leverage to peak in the third quarter of 2026 after completing its Kimberly-Clark transaction, and is prioritising debt reduction over new capacity.
- Hardwood pulp price increase of USD 50 per tonne in the Americas and Europe and USD 20 per tonne in Asia, effective 24 September 2026
- Net debt target lowered to USD 11bn from USD 12bn as of 22 September 2026
- 2026 capital expenditure plan set at USD 2.1bn
- Q2 2026 revenue of BRL 11.59bn and net income of BRL 1.81bn, with adjusted EBITDA of BRL 4.2bn at a 48% margin on pulp sales of 2.9m tonnes